Project Commitment Groups
Overview
To track the progress of the Generation project, individual generating units built as part of a generation project are grouped under the Project Commitment Groups tab for aggregation purposes.
Project Commitment Groups are relevant during the project life-cycle only. Once the group of Generating Units is commissioned and approved for commercial use, they are no longer required or relevant.
When you create a new Project Commitment group, you complete a series of questions related to the project, looking at the specific categories below.
Table 1 Project commitment group categories
Category |
Criteria |
---|---|
Land |
The project proponent has purchased/settled/acquired (or commenced legal proceedings to purchase/settle/acquire) land for the construction of the project |
Contracts |
Contracts for the supply and construction of major plant or equipment components (such as Generating Units, turbines, boilers, transmission towers, conductors, and terminal station equipment) are finalised and executed, including any provisions for cancellation payments |
Planning |
The proponent has obtained all required planning consents, construction approvals, connection contracts (including Generator Performance Standard agreement from AEMO in the form of the 534A letter), and licences, including completion and acceptance of any necessary environmental impact statements |
Finance |
The financing arrangements for the proposal, including any debt plans are concluded and contracts executed |
Construction |
Construction of the proposal must have commenced or a firm commencement date is set Commercial use date for full operation is set |